Wednesday, October 13, 2010
U.S. v. State of New York & Cinergy Corp
Oct 12: In the U.S. Court of Appeals, Seventh Circuit, Case No.  09-3344. More than a decade ago  the Environmental Protection Agency brought this suit  against affiliated owners (i.e. Cinergy  et al) of a number of coal-fired electric power plants in  the Midwest. The suit claims that Cinergy violated section  165(a) of the Clean Air Act, 42 U.S.C. § 7475(a), by  modifying a number of the plants without first obtaining  from the agency a permit that the agency contends was  required by a regulation, 40 C.F.R. § 52.21(a)(2)(iii),  because the modifications were "major" and would produce  increases in emissions of nitrogen oxide and sulfur dioxide.                 
    Cinergy  argued; the regulation does not require a permit for  modifications unless they will increase the  hourly  rate at  which a plant can emit pollutants, even if they will  increase the plant's annual  emissions by enabling the  plant to be operated for more hours during the year. The  district judge rejected Cinergy's interpretation. Without  the required permit, Cinergy was liable for increased  pollution caused by the modifications, and faced the  prospect of an injunction that would require it to shut down  the plants, plus civil penalties of $25,000 for each day  that it had violated the permit requirement.  
      Cinergy took an interlocutory appeal under from the  judge's ruling on the hourly capacity versus actual-emissions interpretation of the regulation. The Appeals Court affirmed that district court decision,  agreeing that the regulation required application of the  actual emissions standard. United States v.  Cinergy Corp., 458 F.3d 705 (7th Cir. 2006). However, the Appeals Court says that one point  in that opinion is worth repeating because it bears on an  issue in the present appeals. 
     The Appeals  Court indicates, "Cinergy's hourly-capacity interpretation would if adopted give a company that had a choice between making a physical modification that would increase  the hourly emissions rate and one that would enable an  increase in the number of hours of operation an incentive to  make the latter modification even if that would produce a  higher annual level of emissions. For that modification  would elude the permit requirement and thus shelter the  company from liability for the increased emissions. It would also distort the choice between  rebuilding an old plant and replacing it with a new one. The  Clean Air Act treats old plants more leniently than new ones  because it is expensive to retrofit a plant with  pollution-control equipment. Wisconsin Elec. Power Co.  v. Reilly, 893 F.2d 901, 909 (7th  Cir. 1990). 
     "But  there is an expectation that old plants will wear out and be  replaced by new ones that will thus be subject to the more  stringent pollution controls that the Act imposes on new  plants. A spur to replacing an old plant is that aging  produces more frequent breakdowns and so reduces a plant's  hours of operation and hence its output unless the owner  invests in continuous, and cumulatively costly, replacement of worn-out parts to keep the plant going. Cinergy's interpretation would if adopted have given the company an artificial incentive instead to renovate its old plants, and by so doing increase their hours of operation, rather than to replace the plants  even if replacing them would cost less. For by renovating  the plants rather than replacing them, the company could  increase their output without having to invest in measures  for preventing the enhanced output from generating increased  pollution."
     The  current case follows a jury trial where the verdict was mixed  requiring fourteen modification projects at three plants  which were at issue; the jury found liability with respect  to four of the projects, all at Cinergy's plant in Wabash,  Indiana, and all undertaken between 1989 and 1992. These  modifications, the jury found, had been likely to increase  the plant's annual emissions of sulfur dioxide and nitrogen  oxide and therefore Cinergy should have sought a  permit.
      However, on appeal, the Appeals Court ruled, "Without expert testimony to support an estimate of  actual emissions caused by the modifications, the government  cannot prevail with respect to the charge of nitrogen oxide pollution; for the government doesn't contest Cinergy's claim that if the testimony of the government's  experts should have been excluded, Cinergy is entitled to judgment. Earlier we said that the government cannot prevail with respect to the plant's emissions of sulfur dioxide. Therefore the judgment must be reversed with instructions to enter judgment for Cinergy. The parties have made other arguments, but they are either too feeble to merit discussion. . .  The cross-appeal is therefore dismissed, while the judgment  in the government's favor is, as we said,  reversed."
     Access the  complete opinion (click  here).
Subscribe to:
Post Comments (Atom)
 












 
 Posts
Posts
 
 


No comments:
Post a Comment