32 Years of Environmental Reporting for serious Environmental Professionals
Tuesday, February 21, 2012
Blue Ridge Environmental Defense League v. NRC
Feb 17:  In the U.S. Court of Appeals, D.C. Circuit, Case No. 09-1112, consolidated with 10-1058. On Petitions for Review of Orders of  the Nuclear Regulatory Commission. In December 1974, Tennessee Valley Authority (TVA) received construction permits from the Atomic Energy Commission, the predecessor  to the Nuclear Regulatory Commission (the NRC or the  Commission), for the Bellefonte Nuclear Plant, Units 1  and 2 (the units). TVA pursued construction under a  series of permit extensions through the late 1980s,  when, based on its projections of diminished energy  demand, it decided to place the units in "deferred  status" and establish a maintenance program under the  NRC's Policy Statement on Deferred Plants (the Policy Statement). Under the Policy  Statement, during a deferral period, a permit holder is  required to undertake maintenance and preservation  activities but may halt actual construction. In 2005, TVA placed the units in "terminated" status under the Policy  Statement. One year later, TVA voluntarily requested  that the NRC withdraw the permits. The NRC granted this  request.               
    In 2008,  TVA asked the NRC to reinstate its withdrawn construction permits. Although neither withdrawal nor reinstatement are specifically addressed in the Atomic Energy  Act (the AEA or the  Act), the NRC granted TVA's  reinstatement request in an order issued on March  9, 2009 and published in the Federal Register on March  13, 2009. 
 On March 30, 2009, the Blue  Ridge Environmental Defense League (BREDL or Petitioner)  filed a petition with the Appeals Court, purporting to  challenge the NRC's decision to reinstate the  construction permits. However, the Appeals Court notes that, ". . .in its  Statement of Issues To Be Raised, in its Reply Brief,  and during oral argument, BREDL insisted that it was not  challenging the NRC order that was published in the Federal Register on March  13, 2009. Rather, BREDL  asserted that its March 30, 2009 petition for review challenges only a compilation of 'Response Sheets' filed by  individual Commissioners in December 2008 and January  2009."
     The Appeals Court said that BREDL contends that the compilation of  Commissioners' views resulted in a final order on  January 27, 2009. However, the Appeals Court said, "We disagree. After the Commissioners' 'Response Sheets' were  assembled, the matter was referred to the NRC staff for  evaluation. However, it was not until February 18, 2009  that the NRC authorized the staff to issue an order on  behalf of the agency reinstating the construction  permits. That order was published in the  Federal Register on March 13, 2009. Therefore, BREDL's petition for review challenging  an alleged action of the NRC taken on January 27, 2009  does not seek review of a final NRC  order."
      The Appeals Court rules, "Under  the Hobbs Act, this court has jurisdiction to review only 'final orders' of the NRC. 28 U.S.C. § 2342(4) (2006).  The March 30, 2009 and March 8, 2010 petitions filed by  BREDL with this court do not seek review of final NRC  orders. Therefore, we lack jurisdiction and must  dismiss."
     Access the complete opinion  (click  here). [#Energy/Nuclear,  #CADC]
 GET THE REST OF TODAY'S  NEWS (click  here)
32 Years of Environmental Reporting for serious Environmental Professionals
32 Years of Environmental Reporting for serious Environmental Professionals
Shenandoah Valley Network v. J. Capka
Feb 17: In the U.S. Court of  Appeals, Fourth Circuit, Case No. 10-1954. Appealed from the United  States District Court for the  Western District of Virginia, at Charlottesville. The Appeals Court explains  that the Federal Highway Administration (FHWA) and the Virginia Department of Transportation (VDOT) (collectively,  the Agencies) are planning improvements to Virginia's  Interstate 81 corridor using a tiered review process.  Appellants -- a group of environmental and preservation  organizations -- challenged the Agencies' execution of  the tiered process, alleging various constitutional and  statutory violations. The  district court rejected these challenges and granted  summary judgment in favor of the Agencies.           
    On  appeal, appellants claim that the Agencies are attempting to foreclose consideration of environmentally friendly alternatives for specific sections of I-81 by choosing a corridor-wide improvement concept in the first stage of the  review process. Appellants, however, misapprehend the  Agencies' position. As confirmed at oral argument, the  Agencies plan to comply with the Stipulation in this  case and the National  Environmental Policy Act (NEPA), by considering  site-specific alternatives to the corridor-wide  concept in subsequent stages. The Appeals Court ruled, "Because there is  no actual dispute here, and because appellants cannot  show any injury or imminent threat of injury, this suit  is not justiciable. Accordingly, we must dismiss the  appeal."
     The  Appeals Court concluded further, "There is simply nothing for this court to  adjudicate. NEPA does not permit us to prescribe  outcomes either now or in the future, but neither would  it allow us to proscribe in the present proceeding even  the consideration of future environmental impacts.  Either the prescription of outcomes or the proscription of consideration would not only be contrary to the statute,  but would raise a live and present controversy between  the parties. Neither circumstance being present, there  remains nothing to dispute  and we are satisfied that no justiciable controversy lingers. Accordingly, the appeal is  dismissed."
      Access the complete opinion (click  here). [#Transport,  #CA4]
 GET THE REST OF TODAY'S  NEWS (click  here)
32 Years of Environmental Reporting for serious Environmental Professionals
32 Years of Environmental Reporting for serious Environmental Professionals
Turtle Island Restoration Network v. Department of State
Feb 17: In the U.S. Court of  Appeals, Ninth Circuit, No. 10-17059. Appealed from the United States District Court  for the Northern District of  California. Turtle Island  Restoration Network (TIRN), a non-profit environmental organization, appeals  from the district court's dismissal of its claim on res judicata grounds [i.e.  once a matter is judicially decided, it is finally decided]. TIRN alleges  that the U.S. Department of State failed to satisfy its  consultation and environmental assessment obligations  under the National Environmental Policy Act (NEPA)  and the Endangered Species Act (ESA),  in conducting annual certifications of  countries exempted from the general ban on shrimp imports.            
    Section  609(b) of Public Law 101-162 prohibits the importation of shrimp harvested with technology that may adversely affect sea turtles, except from countries certified to employ a  turtle protection program comparable to that of the  United States. The Appeals Court said, "We must decide whether TIRN's current lawsuit for NEPA and ESA violations is precluded by its earlier lawsuits challenging  the State Department's regulations implementing the  section 609(b)(2) certification  process."
     The  Appeals Court concludes, "Because TIRN's current challenge to the State  Department's section 609(b)(2) certification process  arises from the same transactional nucleus of facts as  its earlier litigation, res judicata bars its claims.  Accordingly, we affirm the district court. Although TIRN forfeited its opportunity to challenge the State Department's non-compliance with NEPA and ESA  obligations in section 609(b)(2) certifications, our decision  doesn't preclude judicial review of this issue. Because  the legal question of whether NEPA and ESA apply to  section 609(b)(2) has yet to be litigated on the merits,  another plaintiff -- not in privity with TIRN -- is  still free to bring this challenge."
     Access  the complete opinion (click  here). [#Wildlife, #CA9]
 GET THE REST OF TODAY'S  NEWS (click  here)
32 Years of Environmental Reporting for serious Environmental Professionals
32 Years of Environmental Reporting for serious Environmental Professionals
Subscribe to:
Comments (Atom)
 












 
 Posts
Posts
 
 

